Skip to content
Environmental Cleanup of 150 Sohier Road
Beverly Massachusetts

Updated 4-6-2026

This website provides information about the environmental cleanup of the property located at 150 Sohier Road in Beverly, Massachusetts. Investigation and treatment of the site is being conducted in accordance with Massachusetts General Law 21E and the Massachusetts Contingency Plan (310 CMR 40.0000). The site is listed with the Massachusetts Department of Environmental Protection (MassDEP) as site number 3-0000485, Varian-Microwave Div., and reports can be found in the MassDEP data portal under “Supporting Documents.” 

Varian Installing and Starting Up Environmental Treatment Systems

In recent years, environmental investigations and cleanup of the former Varian site have progressed rapidly. Prior investigations and treatment have been conducted at the site since the 1990s. These efforts were renewed and enhanced starting in 2021. Since then, the Varian project team has worked with the community and MassDEP to conduct additional investigations of indoor air, surface water and sediment, groundwater, soil, and bedrock. An updated risk assessment has been completed based on the additional data.

The risk assessment concluded that site contaminants pose no “significant risk” for local residents and current workers at the former Varian property, with the existing soil vapor treatment systems operating on the property.

Additional treatment is required under state cleanup laws to prevent potential future risk and to limit the future migration of contaminants. The project team has identified and selected updated treatment alternatives for five areas, prepared detailed implementation plans, and begun installing and operating these systems.

“No Significant Risk” is a regulatory term based on site data. It describes when a contaminant is not present or exists below a level that would cause a defined level of increased risk to human health or the environment.

home_image1e

Figure 1 Site Map and Selected Treatment Areas

Public Outreach

The next public involvement plan (PIP) meeting will be held on May 12, 2026. The February 2026 Phase IV Status Report will be presented along with a remedial construction progress update. Please see meeting notice.

Treatment System Progress

Environmental cleanup is focused on six project areas (figure 1) and summarized below. More information about cleanup progress can be found on our Environmental page.

Building 3 Thermal Treatment

Status: The selected remedy – thermal treatment – was presented in the Phase IV Remedy Implementation Plan (Part 1) and at the June 2023 public meeting. Upon design completion, drilling of thermal wells began in December 2023. In January 2025, exterior drilling was completed, and interior drilling began.

Current and upcoming work: Interior drilling has continued through March and is expected to finish later this month (April). Aboveground treatment equipment installation is also ongoing and expected to continue through the spring. We expect the thermal treatment system will begin operation next month (May).

Stream A Granular Activated Carbon Adsorptive Barrier

Status: The selected remedy – a granular activated carbon adsorptive barrier – was presented in the Phase IV Remedy Implementation Plan (Part 1) and at the June 2023 public meeting. The carbon mats were installed in October 2023.

Current and upcoming work: Field inspections are performed routinely to assess the condition of the mats.

PSL-10 Subgrade Biogeochemical Reactor

Status: The selected remedy – a subgrade biogeochemical reactor (SBGR) – was presented in the Phase IV Remedy Implementation Plan (Part 3) and at the November 2023 public meeting. Following its installation, operation of the SBGR began in April 2025.

Current and upcoming work: The SBGR continues to operate. The next round of post-treatment sampling is scheduled for May 2026. The sampling results will be provided in the next Phase IV Status Report.

Bedrock In Situ Chemical Reduction

Status: The selected remedy – in situ chemical treatment – was presented in the Phase IV Remedy Implementation Plan (Part 2) and at the November 2023 public meeting. Some minor changes in the remedial injection amendment (in situ chemical reduction or ISCR) were documented in the September 2024 Revised Phase IV Status Report and presented at the September 2024 public meeting. Final selection of the remedial additives for this area was outlined in the Modified Phase IV Plan presented at the May 2025 public meeting.

Current and upcoming work: Stages 1 and 2 of the bedrock treatment are complete. The next post-treatment sampling is scheduled for May 2026. The sampling results will be provided in the next Phase IV Status Report. Drilling for Stage 3 bedrock treatment is anticipated to start this spring with treatment to follow.

Building 5 Bioremediation

Status: The selected remedy – bioremediation – was presented in the Phase IV Remedy Implementation Plan (Part 2) and at the November 2023 public meeting. The Basis of Design for Building 5 treatment was included in the August 2025 Phase IV Status Report. Investigation and treatment beneath the building are being completed simultaneously, and pressure injections are used to increase the influence of the treatment.

Current and upcoming work: Drilling for treatment began in late January 2026. Treatment injections were completed at the first location in February 2026 and the second location in March 2026. Drilling and treatment at the third location will begin in April, with the fourth location to follow. The first round of post-treatment groundwater sampling will be conducted in May 2026, and the results will be presented in the next Phase IV Status Report.

Site-Wide Sampling

Site-wide sampling of wells and stream locations is planned for May 2026. The sampling results will be documented in the next Phase IV Status Report.

Site History and Overview

The former Varian Facility, located at 150 Sohier Road, is currently owned by another firm and operated as an active manufacturing facility for microwave and radar products.

The 150 Sohier Road property has been used as an industrial facility since the early 1950s. Industrial solvents were released to the environment due to the chemical handling and disposal practices that were common at the time, before more strict environmental regulations were enacted. These solvents, used primarily for surface treatment, cleaning, and degreasing operations, included trichloroethene (TCE), perchloroethene (PCE), and 1,1,1-trichloroethane (TCA). Releases of these solvents occurred in three main areas: the Building 3 area, the Building 5 area, and an open field known as PSL-10.

TCE, PCE, and TCA are heavier than water and have limited ability to dissolve in water. For that reason, they are often referred to as “dense nonaqueous phase liquids” (DNAPLs). They also tend to evaporate easily and are referred to as volatile organic compounds or VOCs.

Our Commitment

Varian is committed to conducting response actions according to the Massachusetts Contingency Plan, engaging stakeholders, and keeping the community informed of progress.

© 2022 Varian Medical Systems, Inc. All Rights Reserved.

Production of any of the material contained herein in any format or media without the express
written permission of Varian Medical Systems is prohibited.